Understanding Motor Duty Rating 

By on

One of the comments on my Motor Starting Series was asking for something on duty cycles.  Here it is. 

As a purchaser of a motor, you have responsibility to let the manufacturer know the anticipated duty of the motor.  To assist in the communication of this information, the standard IEC 60034-1 (Rotating electrical machines) defines several duty characteristics, denoted S1 to S10:

S1  Continuous duty The motor operates at a continuous load for sufficient time to enable machine to reach thermal equilibrium. 
S2 Short Time duty Operation at a load for a time not sufficient to reach thermal equilibrium, followed by enough time for the motor to cool down.
S3  Intermittent periodic duty
Series of identical duty cycles each a constant load for a period, followed by a rest period. Thermal equilibrium is not reached during the cycle.
S4 Intermittent periodic duty with starting Similar to S3, but there is a significant starting time within the periodic operation.
S5 Intermittent periodic duty with electric braking Sequence of identical duty cycles - starting, operation, braking and rest.  Again thermal equilibrium is not reached.
S6 Continuous operation periodic duty Identical duty cycles with a period at load followed by a period at no load.  Difference between S1 is that the motor runs at no-load, without actual stopping.
S7 Continuous operation periodic duty with electric braking As per S6, but with a significant starting and electric breaking periods.  Again motor operates at no-load for  period instead of stopped. 
S8 Continuous operation periodic duty with related load/speed changes Series of identical repeating duty cycles, where within each cycle the motor operates at several different load levels and speed. There is not stopped time and thermal equilibrium is not reached.
S9 Duty with non-periodic load and speed variations     Load and speed vary periodically within the permissible operating range. Frequent overloading may occur.
S10 Duty with discrete constant loads and speeds Duty with discrete number of load/speed combinations, with these maintained long enough to reach thermal equilibrium.
     

 

Thermal Equilibrium is the state reached when the temperature rise of the machine does not vary by more than 2K per hour.   If you don't specify the duty cycle, the manufacturer will likely assume S1. Click on the image to see a larger version, illustrating the duty cycles.

If anyone has anything to add, please do so below. 



Steven McFadyen's avatar Steven McFadyen

Steven has over twenty five years experience working on some of the largest construction projects. He has a deep technical understanding of electrical engineering and is keen to share this knowledge. About the author

myElectrical Engineering

comments powered by Disqus

  1. sabari nath's avatar sabari nath says:
    5/24/2013 7:51 AM

    Can you help me understand the relation between Motor duty cyce and Starts per hour?


Comments are closed for this post:
  • have a question or need help, please use our Questions Section
  • spotted an error or have additional info that you think should be in this post, feel free to Contact Us



Copyright Infringement

myElectrical does not support or promote the use of copyrighted material without the copyright owner's consent. If you believe that material for which...

Capacitors - Energy Storage Application

Capacitors have numerous applications in electrical and electronic applications.  This note examines the use of capacitors to store electrical energy....

The dc resistance of conductors

This is the first of two posts on the resistance of conductors. In the next post I will look at the ac resistance, including skin effect and we deal with...

E-Ink

Before the technical, some general information. E-ink display are found in a lot of e-readers, some mobile phones and similar devices and the intent is...

Fault Calculations - Typical Equipment Parameters

A frequent problem in fault calculations is the obtaining of equipment parameters.  While it is always preferable to use the actual parameters of the equipment...

IEC Document Designation

Often document control is dictated by project requirements, for example a particular organisation may have an existing numbering system. Existing company...

Write your best report

Years ago I was told that you should always try to write the best report you can.  Many years later I still think on this as one of the better pieces of...

What happened to the cable notes?

If you are wondering what happened to our cable notes, the short answer is that we have moved them to myCableEngineering.com.  The "Knowledge Base" at...

Electric Motors

Collection of links to various places with useful motor information. I’ll try and return to the page every now and again to update it with any motor notes...

How to Check a Circuit is Dead

If you want to check a circuit is dead (not live), you should always use the three point method. First check a known live circuit, then check the dead...

Have some knowledge to share

If you have some expert knowledge or experience, why not consider sharing this with our community.  

By writing an electrical note, you will be educating our users and at the same time promoting your expertise within the engineering community.

To get started and understand our policy, you can read our How to Write an Electrical Note