Equipment Verification (to IEC Standards) 

By on


KEMA High Power Laboratory, Netherlands
One of the requirements to ensuring that everything works is to have equipment selected, manufactured and verified [tested] to IEC standards. Not all equipment out there meets this requirements. It is the responsibility of the engineers in the procurement and construction process to ensure that only equipment meeting these requirements is used.

If your involved in this activity you most likely already know what to do and have your own methods for approaching this issue. If your new to this or have just been tasked with verifying equipment meets requirements, hopefully this post will get you started.

Ensuring compliance is not complicated, but there are a couple of things you aware of.

The first is the requirements themselves. Project specifications will often say equipment needs to be manufactured to xyz standard and often stop at that. To fully understand the requirements you need to know what is in xyz standard – which means reading it. The IEC standards in general are pretty good as giving performance requirements and listing the necessary testing and verification activities which need to be carried out. By reading the standard you can gain a really good understanding of what is required to show than an item of equipment will meet the standard.

The second thing to look at is ensuring that the equipment actually does meet the standard. In principal this is achieved by confirming that the equipment has undergone the necessary testing and verification as required by the standard. Generally this falls into two categories:

  1. Type testing and design verification – which is carried out on samples of the product (not necessarily the items to be sold to the customer). This level of testing is generally expensive and is carried out to demonstrate that the general concepts and arrangements of equipment meets the performance requirements of standard.
  2. Routine testing – carried out and each item of equipment which is produces and sold to the customer. This often takes the form of testing at the factory and site testing. It is designed to give confidence that each item of equipment is working as anticipated and that there have been no manufacturing problems introduced.

To confirm that type testing and design verification has been achieved, results of testing from independent third party laboratories are normally accepted. The IEC maintains a list of laboratories (by country) which have been approved to certified to approve compliance with standards. It is advisable to insist on only using certificates from approved laboratories:

Routine testing will cover items as required by the standard and will often involve additional testing as required by the project. This is normally carried out by the manufacturer, but can be a third party if required by the project. These may or may not be witnessed by the project engineers (although usually will be in the case of important equipment).

That’s all there is to it. In practice there is a lot of equipment which does not meet standard out there and pushers of this equipment will be tricky in trying to convince you that it is ok. By following the above, you should be in a position to spot equipment which does not meet standard and ensure that your project is supplied only with reputable equipment.



Steven McFadyen's avatar Steven McFadyen

Steven has over twenty five years experience working on some of the largest construction projects. He has a deep technical understanding of electrical engineering and is keen to share this knowledge. About the author

myElectrical Engineering

comments powered by Disqus



IEC Document Designation

Often document control is dictated by project requirements, for example a particular organisation may have an existing numbering system. Existing company...

Paths of Flight

GE have put together a time-lapse video shown flight take-off and landings at some airports. An interesting view:

Occam's Razor

I was reminded of Occam's Razor while reading a book. It's quite a simple principal of logic which has stood the test of time and is accepted as central...

Voltage Levels – Confused?

I was having a conversation the other day about voltage levels.  While everyone was in agreement that low voltage was 1000 V and less, there was more confusion...

IEC 60287 Current Capacity of Cables - An Introduction

IEC 60287 "Calculation of the continuous current rating of cables (100% load factor)" is the International Standard which defines the procedures and equations...

ABB Technical Guides - Motor Operation

ABB has produced a range of technical guides that offer concise explanations of the major technologies and technical issues in low voltage AC drives. ...

How to Size Power Cable Duct

Some colleagues had an issue earlier in the week on sizing conduits to be cast in concrete for some power cables . It became clear that none of us had...

1,000 kV UHV First for China

At the beginning of the year China put the world's first 1,000 kV UHV transmission system into operation. Transmitting power at over a million volts is...

Understanding Circuit Breaker Markings

IEC 60947 is the circuit breaker standard and covers the marking of breakers in detail. Any manufacturer following this standard should comply with the...

9 power supply issues solved by using a UPS

Installation of a UPS can help in reducing problems due to issues with the power supply.  A lot of people relate this to nine key issues.  Depending on...

Have some knowledge to share

If you have some expert knowledge or experience, why not consider sharing this with our community.  

By writing an electrical note, you will be educating our users and at the same time promoting your expertise within the engineering community.

To get started and understand our policy, you can read our How to Write an Electrical Note