UPS Sizing - Rules of Thumb 

By on

Not so long ago I was telling someone that I don't use rules of thumb as most things are easily calculated anyhow.   As it turns out last week I ended up sizing some UPS using what can only be described as rules of thumb.   In deference to my change of heart here are my UPS sizing rules of thumb.

First rule; kW and kVA are related by 0.8.  This does not apply to all UPS, but it does for many (and is the worse case).  People often get confused with what this means, so I'll try to explain it a little.  Each UPS has a maximum kW and kVA it can deliver (related by 0.8), for example a 100 kVA UPS can deliver a maximum of 100 kVA or maximum of 80 kW.  Some examples will make this more clear (assuming a 100 kVA, 80 kW UPS):

  • load is 80 kW at 0.7 power factor = 114 kVA - exceeds maximum kVA
  • load is 80 kW at o.8 power factor = 100 kVA - UPS is good
  • load is 80 kW at 0.9 power factor = 88 kVA - UPS is good
  • load is 100 kVA at 0.7 power factor = 70 kW - UPS is good
  • load is 100 kVA at 0.8 power factor = 80 kW - UPS is good
  • load is 100 kVA at 0.9 power factor = 90 kW - exceeds maximum kW

Some people work in kVA, but I always choose to work in kW.  kW is the measure of power used by the equipment and it make sense to me to use that. It can also be added arithmetically to give a technically correct answer (kVA cannot as it is a vector quantity). Once I have the final load kW, divide by 0.8 to get the kVA and select the next largest standard UPS size.

I used to size UPS systems to run at full capacity.  Many individuals and institutions like to limit the loading on a UPS to 90% of it's rated full load current.  After much arguing I have decided to hold my hand up, surrender and follow the same rule. Given a load requirement in kW, I divide by 0.9 (90% rule) to get the kW to size the UPS.

The charging of batteries (if discharged) and losses/efficiency of the UPS itself mean that input power to the UPS is larger than the output.   UPS units are invariably rated on output power and this needs to be adjusted to determine the loading on the supply system.  Typically allowing 20% for battery charging and UPS losses is a good approach - more than required, but not excessively so. 

Finally in larger installations the above is combined with the black art of selecting the correct size and number units.  Space, cost, redundancy, etc. all affect the final selection.  Is a single 300 kVA UPS better or worse than two 150 kVA units.  How do two 300 kVA units in N+1 redundancy compare with three 150 kVA units in N+1 redundancy. When selecting the UPS for larger installation it can be difficult.  Unfortunately I don't have any rules for this.  I try to look at the system as a whole (power to the UPS, how the UPS power is to be distributed, redundancy requirements, etc.) and put a few configurations on paper. As these are developed into a workable concept one of the options tends to become the obvious one to choose.

Example

Finally here is an example of how the selection may go:

  • requirements - 166 kW of UPS load, N+1 redundancy required
  • selection - 90% rule requires 184 kW which at 0.8 = 230 kVA

Some options would include 2x250 kVA or 3x120 kVA or 4x80 kVA (each giving N+1 redundancy).   The later options require more units but results in less installed UPS kVA (cost would likely be comparable).  I generally prefer smaller units as they are easier to handle/move around, and in this instance I would be tempted to select the 3x120 kVA option.  I think the 4x80 kVA option would be pushing the boundary; while it still maintains N+1, the chance of one of four failing is greater than one of three (taken to extreme 23x10 kVA units is obviously not feasible).     

Summary

As the example shows, the rules of thumb (90% and 20%) give a required kW on which to base UPS selection and input power to the UPS.  kW and kVA are related by 0.8.   In larger installations there is no right or wrong selection of the size and number of UPS units.  Different engineers will likely arrive at different, but still workable solutions.   This mixture of experience and engineering art is not dependant on decimal accurate figures and values obtained by using simple rules of thumb are generally sufficient. 

Related Links



Steven McFadyen's avatar Steven McFadyen

Steven has over twenty five years experience working on some of the largest construction projects. He has a deep technical understanding of electrical engineering and is keen to share this knowledge. About the author

myElectrical Engineering

comments powered by Disqus

  1. Notes's avatar Notes says:
    8/21/2013 3:21 PM

    Trackback from Notes

    A UPS is an uninterruptible power supply.  It is a device which maintains a continuous supply of electrical power, even in the event of failure of the mains (utility) supply.  A UPS is installed between the mains supply and the equipment to be protected... ...


Comments are closed for this post:
  • have a question or need help, please use our Questions Section
  • spotted an error or have additional info that you think should be in this post, feel free to Contact Us



Tips for a better Low Voltage Protection Discrimination Study

Carrying out a protection system discrimination study is critical to ensure the correct functioning of  the electrical system in the event of faults. ...

How a Digital Substation Works

Traditionally substations have used circuit breakers, current transformers (CT), voltage transformers (VT) and protection relays all wired together using...

Batteries

A battery consists of one or more cells, each of which use stored chemical energy to produce electrical energy, There are many types of cells and these...

Low Voltage Switchroom Design Guide

Low voltage (LV) switchrooms are common across all industries and one of the more common spatial requirements which need to be designed into a project...

Earth Electrode Resistance

Earthing of electrical systems is essential for the correct functioning and the protecting of life and equipment in the event of faults.  The earth electrode...

ABB Technical Guides - Motor Operation

ABB has produced a range of technical guides that offer concise explanations of the major technologies and technical issues in low voltage AC drives. ...

Nikola Tesla

Nikola Tesla was born exactly at midnight on July 10, 1856 in the tiny village of Smiljan, Lika in Croatia. In his late teens, Tesla left the village to...

Autonomous Vehicle Challenge

Two driverless and solar power vans have departed from Italy on their way to China via the silk road. During the 13,000 kM trip the vans will drive themselves...

Low Voltage Fault Tables

The following tables provide quick order of magnitude fault levels for a a range of typical low voltage situations.

How to Calculate Motor Starting Time

Request to look at induction motor starting time have come up a few times on the site. Hopefully in this post, I give you guys some idea on how to calculate...

Have some knowledge to share

If you have some expert knowledge or experience, why not consider sharing this with our community.  

By writing an electrical note, you will be educating our users and at the same time promoting your expertise within the engineering community.

To get started and understand our policy, you can read our How to Write an Electrical Note