Periodic Electrical Installation Inspection – What to Inspect? 

By on

This is the second post in a series of two on periodic electrical inspections. In the first post, I discussed how often inspections should be carried out. If you missed that post, you may want to read it now:

Periodic Electrical Installation Inspection
– How Often?

As with how often, when looking at what to inspect there are two considerations – 1) inspection of systems, which businesses themselves have decided are critical to their operation and 2) the minimum systems which need to be inspected according to regulations.

The aim of any inspection is to ensure that the equipment is still maintaining the safety of persons, protecting equipment and property, providing the correct level of business continuity and has not been damaged or subject to defects.

Regulations such as the IEE Wiring Regulations in the UK and the National Electric code in the US give guidance on the level and detail of the inspection. Regulations tend to deal predominately with the safety of persons and property. Depending on the nature of the installation, it may be prudent for the owner to go beyond regulation by carrying out additional inspections to ensure business continuity.

Inspections will consist of visual investigations, supplemented by testing (for example checking the disconnection of times of protective relays).

  • In the UK, IEE Guidance Note 3, Inspection & Testing, lists items which should be considered for inclusion in any inspection and testing routine:
    • Inspection – joints, conductors , switchgear, fire barriers, extra low voltage systems, basic protection, protective devices, enclosures, marking and labelling
    • Testing – protective/bonding/ring-circuit conductor continuity, insulations resistance, polarity, earth electrode resistance, earth fault loop impedance and functional tests (RCD, circuit breakers)

In determining the extent of inspection and testing, considerable care needs to be taken to ensure everything is covered. On large installations, inspection and testing may cover a sample of the system – with subsequent inspections covering different portions of the system.

Inspections and testing will be carried out around live equipment and only suitably qualified personnel should be doing this work. Records and test results should be kept to verify that periodic inspections have been carried. Inspection and testing records can also be compared across time to evaluate changes in systems and aid in planning maintenance.



Steven McFadyen's avatar Steven McFadyen

Steven has over twenty five years experience working on some of the largest construction projects. He has a deep technical understanding of electrical engineering and is keen to share this knowledge. About the author

myElectrical Engineering

comments powered by Disqus



Three Phase Power Simplified

A single phase system is perhaps the most common type of system most people are familiar with. This is what people have in their homes and what appliances...

Inductance

When current flows within a wire, a magnetic field is created. The potion of this magnetic field perpendicular to the wire is called the magnetic flux...

Useful Motor Technical Information

Sometimes it’s useful to be able to quickly lookup a piece of technical information.  This note is a collection of information related to motors, and in...

Power Factor

Power factor is the ratio between the real power (P in kW) and apparent power (S in kVA) drawn by an electrical load. The reactive power (Q in kVAr)...

Material Properties

Everything physical in electrical engineering from insulations to conductors revolves around materials. Here we are listing common materials along with...

Fault Calculation - Symmetrical Components

For unbalance conditions the calculation of fault currents is more complex. One method of dealing with this is symmetrical components. Using symmetrical...

Nikola Tesla

Nikola Tesla was born exactly at midnight on July 10, 1856 in the tiny village of Smiljan, Lika in Croatia. In his late teens, Tesla left the village to...

Cable Trumps

Bored at work and would rather be playing trump card game with you son. The next best thing (or not) maybe the online cable trump card game from AEI Cables...

Microsoft OneNote

A couple of months ago I came Microsoft's OneNote and downloaded the 60 day free trail. Since then I have been using it regularly and now have a full license...

Autonomous Vehicle Challenge

Two driverless and solar power vans have departed from Italy on their way to China via the silk road. During the 13,000 kM trip the vans will drive themselves...

Have some knowledge to share

If you have some expert knowledge or experience, why not consider sharing this with our community.  

By writing an electrical note, you will be educating our users and at the same time promoting your expertise within the engineering community.

To get started and understand our policy, you can read our How to Write an Electrical Note.