Periodic Electrical Installation Inspection – What to Inspect? 

By on

This is the second post in a series of two on periodic electrical inspections. In the first post, I discussed how often inspections should be carried out. If you missed that post, you may want to read it now:

Periodic Electrical Installation Inspection
– How Often?

As with how often, when looking at what to inspect there are two considerations – 1) inspection of systems, which businesses themselves have decided are critical to their operation and 2) the minimum systems which need to be inspected according to regulations.

The aim of any inspection is to ensure that the equipment is still maintaining the safety of persons, protecting equipment and property, providing the correct level of business continuity and has not been damaged or subject to defects.

Regulations such as the IEE Wiring Regulations in the UK and the National Electric code in the US give guidance on the level and detail of the inspection. Regulations tend to deal predominately with the safety of persons and property. Depending on the nature of the installation, it may be prudent for the owner to go beyond regulation by carrying out additional inspections to ensure business continuity.

Inspections will consist of visual investigations, supplemented by testing (for example checking the disconnection of times of protective relays).

  • In the UK, IEE Guidance Note 3, Inspection & Testing, lists items which should be considered for inclusion in any inspection and testing routine:
    • Inspection – joints, conductors , switchgear, fire barriers, extra low voltage systems, basic protection, protective devices, enclosures, marking and labelling
    • Testing – protective/bonding/ring-circuit conductor continuity, insulations resistance, polarity, earth electrode resistance, earth fault loop impedance and functional tests (RCD, circuit breakers)

In determining the extent of inspection and testing, considerable care needs to be taken to ensure everything is covered. On large installations, inspection and testing may cover a sample of the system – with subsequent inspections covering different portions of the system.

Inspections and testing will be carried out around live equipment and only suitably qualified personnel should be doing this work. Records and test results should be kept to verify that periodic inspections have been carried. Inspection and testing records can also be compared across time to evaluate changes in systems and aid in planning maintenance.



Steven McFadyen's avatar Steven McFadyen

Steven has over twenty five years experience working on some of the largest construction projects. He has a deep technical understanding of electrical engineering and is keen to share this knowledge. About the author

myElectrical Engineering

comments powered by Disqus



ANSI (IEEE) Protective Device Numbering

The widely used United Sates standard ANSI/IEEE C37.2 'Electrical Power System Device Function Numbers, Acronyms, and Contact Designations' deals with...

Dielectric loss in cables

Dielectrics (insulating materials for example) when subjected to a varying electric field, will have some energy loss.   The varying electric field causes...

Frame Leakage Protection

While not as popular as it once was, frame leakage protection does still have some use in some circumstances.  In essence frame leakage is an earth fault...

Standard Cable & Wire Sizes

IEC 60228 is the International Electrotechnical Commission's international standard on conductors of insulated cables. Among other things, it defines a...

Welcome back Bottle

‘Kept looking at a card, y’see? Kept looking at it. Welcome back Bottle. Gods below welcome home. The Crippled God A Tale of the Malazan Book of the...

Copyright Infringement

myElectrical does not support or promote the use of copyrighted material without the copyright owner's consent. If you believe that material for which...

Restricted Earth Fault Protection

The windings of many medium and small sized transformers are protected by restricted earth fault (REF) systems. The illustration shows the principal of...

Mobile Phones (Brick to Implant)

The mobile phone was born in 1973. They were the size of a brick and weighed a couple of kg, making them difficult to fit into your pocket. At a few thousand...

Equipment Verification (to IEC Standards)

One of the requirements to ensuring that everything works is to have equipment selected, manufactured and verified [tested] to IEC standards. Not all equipment...

Windows Live Writer and myElectrical

When making adding a Note to our site we have a great online WYSIWYG editor and things are pretty simple.  However, if you prefer you can write, manage...

Have some knowledge to share

If you have some expert knowledge or experience, why not consider sharing this with our community.  

By writing an electrical note, you will be educating our users and at the same time promoting your expertise within the engineering community.

To get started and understand our policy, you can read our How to Write an Electrical Note